Staircases have now been assembled at Darley Dale station as the footbridge restoration progresses. The two staircases on the down (Manchester direction) platform have been trial fitted. This allows us to install the lower fixing points, and work can proceed on fitting the landing fill-in panel.
At some point, the stairs will need to be lifted out again, briefly, to allow the span to be installed. However, that is still at Steelway in Wolverhampton with one side nearing completion and work starting on the other side. We are keen to move forward as quickly as possible with what Steelway return to us.
The other two staircases are complete and have been put to one side at Rowsley South. The trial fit of these requires the platform extension to be completed, which and the removal of a location cabinet which contains signalling communications. Work has begun on the up platform (basically restoring it to what it was in British Railway days. Footings have been dug and concrete poured, and stone blocks for the platform facings prepared by hand.
All the on-site work has been undertaken by volunteers and the Trust is indebted to everyone involved for their unstinting hard work to get the footbridge reinstated and operational.